Old Town Residences,
Downtown Dubai
Emrill Services · EnviroSGR
Solid sewage, sewage sludge and associated odours across an 88 m³ treatment basis.
800 litres of EnviroSGR applied over Day 1 and Day 2 for Emrill Services.
outcome
95% odour remediation within 7–10 days; full liquefaction in approximately 2–3 weeks.
View the treatment process
- 01 · Assessment — Survey the contaminant areaReview the site condition, understand the treatment volume and determine the practical application approach.
- 02 · Preparation — Prepare the mixEnviroSGR is loaded into the spray system for controlled application across the waste surface.
- 03 · Application — Day 1 and Day 2 deliveryA total of 800 litres is applied across the two-day process to support surface coverage and biological activation.
- 04 · Remediation — Odour control and liquefactionExpected odour remediation reaches 95% within 7–10 days, with full liquefaction expected in approximately 2–3 weeks.
- 05 · Maintenance — Quarterly preventative strategyWhere suitable, preventative maintenance can be carried out at approximately 25% of the initial cost.